Progress Tracker | LED Modernization Project

LED Modernization
Project

Progress Tracker

Development / Design Pre-Construction

2023-24

Task 1.0

Existing Conditions Survey

  • Prepare complete data set of existing lights to be converted
  • Assess critical maintenance issues
  • Identify repair needs for trolley poles
  • Design and create project website

0%

Task 2.0

Conversion Plan – Phasing and Schedule

  • Product evaluation of industry lighting leaders
  • Review and analyze design of a Network Lighting Management System
  • Develop public engagement material for community outreach
  • Develop conversion plan and schedule for construction

0%

Task 3.0

Construction Documents

  • Prepare a city-wide photometric and gap analysis with equity study
  • Provide streetlight update to ordinance to meet current industry standards
  • Provide summary report of energy and maintenance savings costs
  • Prepare all contractor and vendor bid documents for construction

0%